The Chengdu–Dujiangyan Intercity Railway, also known as the Cheng-Guan Express Railway, starts at the Chengdu North Railway Station and extends westward from the Anjing Station (in Pixian) on the railway’s western ring line. It follows the route of National Highway 317 and the Cheng-Guan Highway, ending in the town of Qingchengshan in Dujiangyan City. There is an interchange with Metro Line 2 at the Xipu Station. The preliminary planned stations are Anjing, Jinniu, Xipu, Hongguang, Pixian East, Pixian West, Ande, Chongyi (reserved), Juyuan, Dujiangyan, and Zhongxing (reserved), with the final destination being Qingchengshan Town.
The Cheng-Guan Express Railway began planning in May 2008. Construction started on November 4 of the same year, and by January 26, 2010, the laying of the entire line’s tracks was completed. On March 1, 2010, the line began comprehensive testing and adjustments; on April 1, it began trial operations; and on May 1, it officially opened to the public for service.
成灌快铁,成都至都江堰铁路起于成都北站,在铁路西环线安靖(郫县)站向西引出后,沿国道317线成灌公路走向延伸,止于都江堰市青城山镇,并与地铁2号线在犀浦同站换乘。初步拟定的站点有安靖、金牛、犀浦、红光、郫县东、郫县西、安德、崇义(预留)、聚源、都江堰、中兴(预留),最后抵达青城山镇。 成灌快铁2008年5月谋动,当年11月4日开建,2010年1月26日全线轨道铺设完毕。2010年3月1日,开始全线联调联试;4月1日,开始全线试运行;5月1日,正式开通运行。

Leave a Reply